The current state of the construction works 24.06.2016

25.06.16

Works on dumping of a ditch and preparation of the pile field under the main process building «Plant growing sturgeons capacity of 250 tons / year of commercial products and 1.5 tons / year of caviar «BIOnika" LLC»»

Blockage of piles for carrying out testing of properties of soil is executed.

1 2